Cellar and Basement Conversion Costs in the UK

What it costs to convert a cellar or dig a new basement in the UK, how waterproofing works, the permissions you need and how long the work takes.

Illustration of a terraced house with a converted cellar

Typical published 2026 figures put the average basement conversion at around £100,000, but the final bill depends largely on your starting point. Converting an existing cellar costs far less per square metre than lowering a floor or digging a brand new basement. This guide explains realistic budget figures, the waterproofing rules you must follow and the permissions you need before a builder starts digging.

A cellar is an existing space below ground, often low and damp, originally built for storage. A cellar conversion makes this space habitable by adding waterproofing, insulation, heating and proper floors. A new basement has to be dug out from scratch beneath your house or garden.

For either project you will normally hire a general builder or main contractor, which is the person or firm managing the site. They hire specialist subcontractors to handle the plumbing, electrics and waterproofing.

Typical cellar and basement conversion costs

Builders price from drawings, a specification and a schedule of works, which is a detailed list of every task and material required. They do not quote from a simple cost per square metre. Per square metre figures are only a way to set an early budget. Published figures differ widely because some cover a basic shell and others a finished room.

The table below shows typical published prices for different types of basement work in 2026.

Type of project

Typical cost per square metre

Typical time on site

Existing cellar conversion

£1,800 to £2,800

8 to 12 weeks

Cellar with lightwell

£2,500 to £4,000

12 to 16 weeks

Lowering an existing floor by 1 to 1.5 m

£3,500 to £5,500

16 to 22 weeks

Brand new basement under the house

£4,500 to £7,500

28 to 40 weeks

These figures are typical published prices for 2026, and your local quotes will differ based on the design, ground conditions, access and the final finish.

Labour is a large share of any job. For a 40 square metre space, a straightforward conversion typically costs £60,000, breaking down to about £500 for materials and £1,000 for labour per square metre. A structural conversion for the same size costs £92,000, and a new basement excavation costs £120,000.

Straightforward conversions range from £30,000 for a 20 square metre space to £90,000 for a 60 square metre space. Structural work ranges from £46,000 to £140,000. Full excavation ranges from £60,000 to £180,000. A typical 30 square metre cellar conversion costs £54,000 to £120,000. In London and the South East, the same 30 square metre conversion is put at £85,000 to £180,000. Separate 2026 figures put London prices typically 20 to 25 per cent higher than elsewhere.

A build quote normally excludes kitchens and bathrooms, flooring and decoration. Professional fees, planning and building control fees, party wall costs and VAT at 20 per cent are also outside a standard build quote. Your budget should include a contingency, which is a reserve fund for unexpected problems. The quote may also include provisional sums, which are allowances for things that cannot be priced yet. You must agree the cost of any variations, which are changes after the price is agreed, in writing before the work happens.

Waterproofing and tanking explained

Waterproofing is the most critical part of the job. The British Standard BS 8102:2022 describes three approaches to protecting below ground structures against water. Designers often combine two of these approaches to keep the space dry.

Type A protection is a barrier applied to the walls and floor, often called tanking. This includes cementitious slurries, renders or sheet membranes applied either internally or externally. Type B is structurally integral watertight construction, such as using concrete with a waterproof admixture. Type C is a drained cavity membrane system that leaves a gap behind the walls and leads water to a sump pump.

A cavity drain membrane system with a sump and pump typically costs £4,000 to £8,000. Sump pump installation costs £1,500 to £3,000 including backup battery systems.

The waterproofing design should come from a specialist, not a general builder. The recognised qualification for a waterproofing designer is CSSW, which stands for Certificated Surveyor in Structural Waterproofing. The Property Care Association keeps a register of waterproofing design specialists.

What pushes the price up

Every basement project is different, but several common factors will increase your final bill.

  • Adding lightwells or external access costs between £5,500 and £10,000.
  • Digging down to lower an existing floor requires heavy machinery and soil removal.
  • Supporting the existing walls with new foundations requires careful engineering.
  • A structural engineer typically charges £1,500 to £3,500 for calculations and drawings, which show how the structure will be supported.
  • Party wall surveyors cost £700 to £1,500 per neighbour if you cannot agree on the work.
  • Rerouting existing drainage pipes adds significant groundworking time.

Planning permission for basements

Planning permission and building regulations are two separate systems, and many projects need one, both or neither. You are unlikely to need planning permission to convert an existing basement into living space. This assumes you do not create a new unit of residential accommodation, change the use significantly to run a business, add a lightwell or alter the external appearance.

Creating a new basement will commonly require planning permission, often because of the effect on the external appearance. A lightwell at the front of the house, visible from the street, may face stricter rules than one at the rear or side. Flats and maisonettes do not have permitted development rights, and conservation areas, listed buildings and properties with planning conditions are more restricted.

In England the householder application fee is £548 from 1 April 2026. Most applications are decided within 8 weeks. Work must start within three years of permission being granted, or five years in Wales. A lawful development certificate gives written proof that a project is permitted development. Scotland and Northern Ireland have their own systems, so check locally.

Building regulations, fire escape and ventilation

Building regulations approval is needed for extensions, loft conversions and most structural and services work. Building regulations apply to works on a basement to ensure the space is safe and structurally sound.

The rules cover fire escape routes, ventilation, ceiling height, damp proofing, electrical wiring and water supplies. Underpinning and foundation work may be needed, and this counts as building work in its own right. You can read more about what underpinning is and what it costs to understand this process.

Approval comes from council building control or a registered building control approver. Certain trades can sign off their own work through a competent person scheme. Gas work needs a Gas Safe registered engineer and electrical work needs a registered electrician. Always confirm membership on the scheme's own register and treat it as a good sign, not a guarantee. You must keep the completion certificate, as it matters when selling the house. Councils can now take enforcement action for up to ten years if you breach the rules. Read our guide to building regulations for home improvements for more detail.

Party walls and your neighbours

The Party Wall etc. Act 1996 applies in England and Wales to work on or near a shared wall or boundary. You must tell your neighbour if you plan to dig below and near the foundation level of their property.

Notice must be given between two months and a year before work starts. The neighbour must reply in writing within 14 days. If you cannot agree, surveyors will draw up a party wall award to govern how and when the work happens.

How long a basement conversion takes

Typical published 2026 timescales on site are 8 to 12 weeks for a standard conversion. Adding lightwells extends this to 12 to 16 weeks. Lowering the floor takes 16 to 22 weeks. A brand new basement under the house takes 28 to 40 weeks.

These timelines only cover the construction phase. Design and approvals add four to six months before construction even begins. Drawings, structural calculations and party wall agreements all take time to arrange before a builder can start digging.

Running costs and maintenance

A waterproofed basement needs ongoing maintenance to stay dry. Sump pump servicing costs £150 to £300 a year. Pumps need replacing every five to ten years at a cost of £800 to £2,000.

Access must be provided for monitoring and maintaining the system. If the pump or its access points are boxed in, the system cannot be checked or serviced, which raises the risk of water getting in if the pump fails.

Choosing a builder and managing the contract

Never choose a builder on price alone. You should gather three written quotes against the same drawings and a detailed schedule of works. A quote is fixed and an estimate is not. Never accept an estimate as if it were a fixed quote, and do not agree to large cash deposits. Cash deals offered without VAT or paperwork leave you with no proof of the contract.

Under the Consumer Rights Act 2015, you are entitled to work done with reasonable care and skill, for a reasonable price and within a reasonable time where none was agreed. You have a 14-day cooling-off period for contracts agreed at home, by phone or online. Paying by credit card can give you Section 75 protection, although it has price limits that most basement projects exceed.

Agree stage payments tied to progress, so you pay in instalments as each stage is finished, and keep back a final payment for completion. Do not pay this final instalment before the snagging is finished, which means finding and fixing minor faults at the end of the job, and you have all the certificates.

The Federation of Master Builders vets and independently inspects members. TrustMark is the government-endorsed quality scheme. Citizens Advice is the signpost for disputes. Under the CDM Regulations 2015 a domestic client's health and safety duties normally pass to the builder. Houses built or refurbished before 2000 may contain asbestos, which must be dealt with by competent people.

Common questions

What is the difference between cellar tanking and waterproofing?

Waterproofing is the broad term for keeping a below ground structure dry. Tanking is a specific type of waterproofing, known as Type A barrier protection, where a waterproof coating or membrane is applied directly to the walls and floor.

Can I lower my cellar floor to get more ceiling height?

You can lower a cellar floor, but it involves digging out the earth and underpinning the existing walls to support the house. Lowering an existing floor by one to one and a half metres costs £3,500 to £5,500 per square metre and takes 16 to 22 weeks.

Do I need a structural engineer for a basement conversion?

You will need a structural engineer if you are lowering the floor, digging a new basement, underpinning walls or removing structural supports. They provide the calculations required for building regulations approval, costing between £1,500 and £3,500.

Do I need to tell my home insurer about a cellar conversion?

Yes. Tell your home insurer before work starts, as building work can affect your cover, and ask the builder for proof of their own insurance.

How do I keep a waterproof cellar dry during a power cut?

A drained cavity system relies on a sump pump to remove water. Ask for a pump with a backup battery, which keeps it running if the mains power fails. Typical published 2026 prices for sump pump installation, including backup battery systems, are £1,500 to £3,000.

Next steps

Before you ask builders to price your basement project, you need to prepare the paperwork and finalise the design.

  • Hire an architect or architectural designer to draw up the plans.
  • Work with a CSSW qualified designer to plan the waterproofing system.
  • Ask a structural engineer for calculations if you are altering the foundations.
  • Check with the council whether you need planning permission for your specific design.
  • Serve notice on your neighbours under the Party Wall Act if you are digging below and near the level of their foundations.
  • Write a schedule of works so every builder quotes for the exact same job.

Once you have your drawings, structural calculations and a clear schedule of works, you can find a builder near you to provide a fixed written quote.

Find a top rated builder near you

3,554 builders across the UK, each ranked on their Google rating and the number of reviews behind it. Start with your county:

All counties and towns · The UK Top 100 builders

Rachel Dawson