How Long Does a House Extension Take to Build?

How long a house extension takes in the UK from first drawings to snagging: design, permissions, finding a builder, the build by type, and what causes delays.

Illustration of an extension shown at foundation, wall and roof stages

Building an extension usually takes a few months of physical work on site. But getting the design drawn up, securing permissions and waiting for a good builder to become available all happen first. This means the whole process from idea to a finished room will take much longer than the building work itself.

You need a realistic timeline so you can plan around your work, finances and living arrangements. While the construction phase is fairly predictable, the planning stages depend entirely on local council processing times and the availability of professionals.

The stages from idea to completion

Every extension project is split into two halves. First is the planning phase, where you hire a designer, apply for the right permissions and source quotes from builders. Second is the construction phase, where the main contractor arrives on site and the physical building happens.

Because every professional and builder will have their own schedule, you need to ask them for their available dates in writing. Nobody can give you a fixed number of weeks for the planning stages until you start making those calls. You must also factor in time to review quotes, sign contracts and arrange your finances.

It is very common to underestimate how long the early stages take. Rushing the planning phase is a mistake that leads to inaccurate quotes and delays later on. Taking your time to get the paperwork right helps avoid delays once work starts.

Design and drawings

Before any builder can give you a firm price or a timeline, they need to see exactly what they are building. This means hiring a professional to draw up plans and write a specification. A specification is a detailed document that lists the exact materials, finishes and standards required for the job. Without it, builders have to guess what you want, which leads to wildly different prices.

You will also need a structural engineer to provide structural engineer calculations. A structural engineer works out the size and strength of the steel beams, joists and foundations needed to keep the building safe. Their calculations support the building regulations application.

The time it takes to get these drawings and calculations done depends entirely on how busy your chosen professionals are. You should ask them how long their current waiting list is before you hire them. Keep in mind that professional fees, planning and building control fees, and party wall costs are normally outside a build quote and must be budgeted for separately.

You also need to decide on the finishes early. Items like kitchens, bathrooms, flooring and decoration are usually outside a standard build quote unless you specifically ask for them to be included. Ordering these items takes time, and late deliveries will hold up the builder.

Planning permission and building regulations timescales

Planning permission and building regulations are two separate systems. Your project might need one, both or neither. You should always confirm the rules with your local council before you start any work. Scotland and Northern Ireland have their own systems, so check locally if you live there.

Many extensions and loft conversions on houses fall under permitted development. This allows you to build within set limits on size, height and position without a full planning application. Flats and maisonettes do not have these rights. Conservation areas, listed buildings and properties with planning conditions are also more restricted.

If your project is permitted development, you can apply for a lawful development certificate. This gives you written proof that the work is permitted development. If you want to build a larger single-storey rear extension, you might be able to go through a process called prior approval.

If you do need a householder planning application, the fee in England is £548 from 1 April 2026. Most householder applications in England are decided within 8 weeks. Once planning permission is granted, work must start within three years in England, or five years in Wales.

Building regulations cover the safety, energy efficiency and structural integrity of the construction. Building regulations approval is different from planning permission, and you need it for extensions, loft conversions and most structural and services work.

You get this approval from council building control or a registered building control approver. If you submit a full plans application, you can expect a decision within 5 weeks, or 2 months with your consent. For smaller projects you can use a building notice, which allows you to begin work two days after submitting it.

You must also consider the Party Wall etc. Act 1996 if you are in England or Wales and building on or near a shared wall or boundary. Getting a party wall agreement in place takes time and must be completed before building starts, which adds to your overall timeline.

Finding and booking a builder

A general builder or main contractor manages the site and brings in specialist subcontractors for trades like plumbing, plastering and electrics. Getting quotes from them takes time. You should always wait until your drawings and specification are finished before asking for prices.

Builders price from your drawings and a specification, not from a cost per square metre. Per square metre figures are only a way to set an early budget, and published figures differ widely because some cover a basic shell and others a finished room. Labour is a large share of any job, and building work in London and the South East costs more.

When a builder gives you a quote, it is a fixed price for the work described. An estimate is not fixed and can easily go up. You should aim to get three written quotes against the exact same drawings. Do not choose on price alone, as cowboy builders who take on more jobs than they can staff can drag a job out.

Good builders can be booked up ahead of time. Their lead time will dictate when your project can actually start, and it varies, so ask for their dates in writing. You should also ask for a schedule of works, which is a programme showing what tasks happen in what order.

You can look for builders who belong to official schemes. The Federation of Master Builders vets and independently inspects its members. TrustMark is the government-endorsed quality scheme. You should confirm membership on the scheme's own register and treat it as a good sign of competence, though it is not a guarantee.

Build time by type of extension

Once the builders arrive, most jobs take between 10 and 18 weeks to complete, though the table below shows shorter and longer figures for particular types. The exact timeline depends on the size of the new space, the complexity of the design and the type of extension you are building.

The table below shows typical build times for different extension types based on standard industry guides.

Type of extension

Typical duration

Single-storey (general)

Around 12 weeks

Single-storey lean-to rear

11 to 13 weeks

Single-storey side return

8 to 10 weeks

Single-storey side

9 to 12 weeks

Single-storey wraparound

10 to 14 weeks

Kitchen extension

5 to 10 weeks or 10 to 14 weeks

Double-storey lean-to

16 to 18 weeks

Double-storey wrap-around

17 to 19 weeks

These durations are typical published figures for 2026. Real timelines will depend on your specific design, ground conditions, site access and the level of finish you choose. Published floor-area figures for a double-storey extension run from 6 to 8 weeks for 20 square metres up to 12 to 14 weeks for 70 square metres, which is shorter than the 16 to 19 weeks in the table, so treat all of these as rough guides.

Larger or more complex builds, such as those needing major groundworks or bespoke glazing, can take 3 to 4 months from groundbreaking to completion.

A week by week single-storey build

To give you a clear idea of what happens on site, here is a standard 14-week timeline for a single-storey extension.

  • Weeks 1 to 4 cover groundwork, foundations, the superstructure, damp-proof course, drains, lintels, concrete floor and insulation.
  • Week 5 is when external walls are built with cavity insulation.
  • Weeks 6 to 7 cover building internal walls, the roof structure and the roof covering.
  • Week 8 is for getting the windows and doors installed.
  • Weeks 9 to 10 see the start of first fix carpentry, plumbing and electrics, followed by opening through to the existing house and fitting the steels.
  • Week 11 is dedicated to plastering followed by about a week for drying out.
  • Weeks 12 to 13 are for second fix work, laying the flooring and fitting the kitchen units.
  • Week 14 is reserved entirely for snagging.

First fix means the hidden carpentry, pipes and wires installed before plastering. Second fix involves connecting the visible items like sockets, light fittings, taps and radiators.

Making the building weathertight is a major milestone. It means the roof is on, the walls are up and the windows are in, so rain cannot get inside and internal work can safely begin. Snagging is the process of finding and fixing minor faults, such as a sticking door or a messy paint finish, before the job is completely finished.

What causes delays

Building work rarely runs perfectly to schedule. Ground conditions are a common cause of early delays. If the builders dig down and find poor soil, old pipes or a high water table, the foundations will take longer and cost more to sort out.

Weather also plays a large part in the UK. Heavy rain, high winds or freezing temperatures can stop bricklaying, concrete pouring and roofing work completely.

The most avoidable delays come from design changes made mid-build. These are called variations. If you change your mind about the layout or the materials after the price is agreed, the builder has to stop, re-price the work, and order new materials. You should always agree the cost of variations in writing before they happen.

Quotes often include provisional sums. These are allowances for things that cannot be priced yet, like a specific type of brick that has not been chosen. If you take too long to make these decisions, the materials will arrive late. You should also keep a contingency fund of extra money to cover unexpected problems.

Scheduling can extend the build if specialist subcontractors are delayed on other jobs. Waiting for local authority building control inspections at key stages can also pause progress. You should check that your builder's timetable allows enough time for plaster and concrete to dry out before the next trade arrives.

Living at home during the work

Many people stay in their house while an extension is built. The early weeks of groundwork and bricklaying happen entirely outside, so your daily life is mostly unaffected.

The disruption starts when the builder breaks through the existing external wall to connect the old house to the new space. A good builder will wait until the new extension is weathertight before doing this. You should expect dust, noise and a lot of tradespeople coming and going.

If you are having a kitchen extension, you will be without cooking facilities for several weeks. You will need to set up a temporary kitchen in another room with a microwave, a kettle and a fridge.

Under the CDM Regulations 2015, health and safety duties for a domestic client normally pass to the builder. They must keep the site safe, but you still need to keep children and pets away from the working areas.

If your house was built or refurbished before 2000, it may contain asbestos. This is a hazardous material that must be dealt with by competent people before the main building work begins.

Snagging and the completion certificate

The final week of the schedule is reserved for snagging and testing. You should set up a contract that uses stage payments tied to progress, and keep a final payment back until completion. Do not pay this final instalment until all the snagging is done and the building control inspector has signed off the work.

You will usually get a completion certificate within 8 weeks of completion of the building work, as long as it complies with the rules. The certificate matters because without it you will not have the certificates of compliance you need when you come to sell your house. Local councils can now take enforcement action for up to ten years if work breaches the regulations.

Certain trades can self-certify their work through a competent person scheme. Electrical work needs a registered electrician and gas work needs a Gas Safe registered engineer. You should check their membership on the scheme's own register.

Under the Consumer Rights Act 2015, tradespeople must provide their service with reasonable care and skill. They must also charge a reasonable price and complete the work within a reasonable time where none was agreed. You also have a 14-day cooling-off period for contracts agreed at home, by phone or online. If you pay a deposit by credit card, you may have Section 75 protection, which has limits on the price of the item. If you hit a dispute, Citizens Advice is the best signpost for help.

Common mistakes to avoid

Many homeowners run into problems because they skip the planning stages or rush into hiring a builder. Avoiding these common errors will keep your project on schedule.

  • Choosing a builder on price alone instead of checking their previous work.
  • Starting work without drawings, a specification or a written contract.
  • Handing over large cash deposits before any materials arrive.
  • Accepting an estimate as if it were a fixed quote.
  • Changing the design mid-build without agreeing the extra cost in writing.
  • Believing a builder who says building regulations are not needed.
  • Accepting cash deals offered without VAT or paperwork.
  • Paying the final instalment before snagging and certificates are done.

Common questions

Do I have to pay VAT on my extension?

VAT at 20 per cent is normally charged on building work, so always check whether a quote includes or excludes it. Cash deals without VAT or paperwork leave you with little to rely on if things go wrong.

What is a schedule of works?

A schedule of works is a detailed list of every task needed to complete the project, in the order it will happen. It helps the builder price the job accurately and gives you a clear idea of what to expect each week. Starting a job without one often leads to arguments over what was included in the price.

Do I need to tell my home insurer?

Yes, tell your home insurance provider before any building work starts and ask in writing what is covered during the works. Cover can be affected by building work, so read your policy wording.

What happens if the builder walks off site?

If a builder disappears, you will need to find another firm to finish the job. This is why you should avoid paying large sums upfront. Stage payments tied to progress mean you pay as work is completed on site.

Next steps for your extension

To get your project moving and secure a realistic timeline, follow these steps before you ask for quotes.

  • Hire an architectural designer to draw up plans and a full specification.
  • Confirm with your local council whether you need planning permission.
  • Submit your plans for building regulations approval.
  • Ask three builders to quote against the exact same drawings.
  • Ask each builder for their lead time and a written programme of works.
  • Set up a contract with stage payments tied to progress on site.

Once you have your drawings and permissions ready, you can start speaking to local firms to see who is available. Take your time to compare their quotes, visit their previous jobs and find a builder near you who can commit to a clear and realistic schedule.

Find a top rated builder near you

3,554 builders across the UK, each ranked on their Google rating and the number of reviews behind it. Start with your county:

All counties and towns · The UK Top 100 builders

Rachel Dawson
Written by
Rachel Dawson Writer

Rachel writes for Top Rated Builders, with a focus on helping homeowners compare quotes and ask the right questions. Away from the desk, she runs a book club with friends.

Looking for a trusted builder? Browse our verified listings.