How Much Does It Cost to Renovate a House in the UK?

What it costs to renovate a house in the UK in 2026 by scope, from a light refresh to a full renovation, with typical costs for rewiring, heating, kitchens and bathrooms.

Illustration of a terraced house half renovated with a skip outside

Typical 2026 prices give a range of roughly £25,000 to £45,000 for a light refresh on a standard three-bedroom UK house, £45,000 to £85,000 for a medium renovation and £85,000 to £150,000 or more for a full renovation. The final price you pay will depend entirely on your design, ground conditions, property access and the finish you choose.

Typical house renovation costs in 2026

Understanding how building firms calculate their prices is the first step to controlling your budget. Builders price from drawings and a specification, not from a generic cost per square metre. A specification is a detailed document listing exactly what materials will be used, down to the type of paint and the brand of sockets. A schedule of works breaks the entire project down into every single task required. You need both of these documents to get an accurate, fixed price from any tradesperson.

The type of professional you hire will also shape your costs. A general builder or main contractor manages the site on a daily basis and brings in subcontractors to do specialised work like plumbing, plastering and electrics.

Labour takes up a large share of any building job. Tradespeople in London and the South East charge higher daily rates than those in other parts of the UK, which pushes up the total cost of any renovation in those areas. The exact condition of your existing property is the final major factor. Stripping a house back to bare brick can reveal hidden problems that must be fixed before the cosmetic work can begin.

Light, medium and full renovation

The following table shows typical published price ranges for a standard three-bedroom house in the UK, broken down by the scale of the work.

Scope of work

Typical 2026 cost

What this usually includes

Light refresh

£25,000 to £45,000

Decorating, flooring, minor repairs, basic kitchen update

Medium renovation

£45,000 to £85,000

New kitchen and bathroom, partial rewire, plastering, flooring

Full renovation

£85,000 to £150,000 or more

Full rewire, new heating, structural changes, high-spec finishes

These are typical published prices for 2026, and your local quotes will differ based on the specific condition of your property.

A light refresh assumes the underlying structure and services are sound. The budget goes mostly on cosmetic updates that you can see and touch. A medium renovation involves modernising the systems that keep the house running, which requires some disruption to the walls and floors. The published full renovation scope includes a full rewire, new heating, structural changes and high-spec finishes.

Cost per square metre and why it varies

Typical published prices show that a house refurbishment typically costs between £500 and £1,500 per square metre. High-end projects can exceed £2,000 per square metre, especially in London. You should only use per square metre figures as a way to set an early budget before you have drawings. They are not accurate enough to use for hiring a builder.

Published figures differ widely because they measure different things. Some per square metre costs cover a basic structural shell, while others cover a completely finished room ready to live in. A builder cannot give you a firm price based on floor area alone because two rooms of the exact same size can have vastly different costs depending on the number of windows, the complexity of the wiring and the quality of the flooring.

Before any new work can begin, the old interior must be removed. Strip out work is costed separately, averaging £15 to £25 per square metre in most areas, and waste disposal can add 20% to 40%. That per square metre figure is for strip out only and should not be mixed with the overall range above. Planning a house renovation step by step ensures you account for these early demolition costs.

Typical costs for the big jobs

The table below shows how the cost of major trades scales with the size of the property. These figures represent the installation and first fix stages of the work.

Job type

Small two-bedroom house

Medium three-bedroom house

Large house (four or more bedrooms)

Electrical first fix (rewire)

£2,000 to £4,000

£3,500 to £8,000

£5,000 to £10,000

Heating first fix

£2,000 to £5,000

£3,000 to £8,000

£5,000 to £12,000

Roof

£3,000 to £7,500

£5,000 to £10,000

£8,000 to £15,000

Windows and doors

£1,500 to £5,000

£2,500 to £8,000

£8,000 to £15,000

Plastering

£3,000 to £7,000

£4,000 to £9,000

£6,000 to £13,000

These figures are typical published prices for 2026. They were compiled separately and should never be added together to create a total house budget, as real quotes depend heavily on the final design.

Many trades are split into two stages. First fix is the hidden work. For plumbing and electrics, this means running the cables and pipes under the floorboards and inside the walls before the plastering begins. Second fix happens later in the project. It involves connecting the visible fixtures, such as fitting the plug sockets, hanging the radiators and installing the light fittings once the walls are finished.

A separate set of whole-house figures puts a partial rewire at £2,500 to £5,000, a full house rewire at £5,000 to £10,000 or more, a new boiler at £2,500 to £4,500 and a full central heating system at £5,000 to £10,000. These were compiled separately, so do not add them to the table above.

Kitchens and bathrooms

Kitchens and bathrooms are two of the larger line items in a renovation budget. The two sets of figures below give different ranges, and the fittings you choose affect the price.

Published prices for a kitchen supplied and fitted run from £5,000 to £10,000 for a budget kitchen, £10,000 to £20,000 for mid-range and £20,000 to £40,000 or more for high-end. Other published figures put a kitchen installation at £5,000 to £8,000 for light, £8,000 to £15,000 for moderate and £15,000 to £30,000 or more for high. The ranges use different assumptions, so treat them as a rough guide.

Bathroom costs scale in a similar way. Published prices put a basic bathroom at £4,000 to £7,000, mid-range at £7,000 to £12,000 and high-spec at £12,000 to £20,000 or more. Other published figures put a bathroom at £3,000 to £6,000 for light, £6,000 to £10,000 for moderate and £10,000 to £18,000 or more for high, per bathroom.

What a renovation quote may leave out

An estimate is just an educated guess, but a quote is a fixed price offer. Even a detailed quote from a reliable builder will normally exclude certain costs that you must pay for separately. If you do not budget for these items, you will run out of money before the house is finished.

A standard build quote normally excludes the following items:

  • Professional fees for structural engineers and surveyors
  • Planning application fees and building control inspection charges
  • VAT at 20 per cent on the builder's labour and materials
  • Party wall agreement costs if you are working near a shared boundary
  • Skip hire and waste disposal charges
  • The supply of the kitchen units and bathroom sanitaryware
  • Final floor coverings like carpets and wood flooring
  • Final painting and wallpapering

Builders use provisional sums in their quotes to cover allowances for things that cannot be priced accurately yet. For example, they might include a provisional sum for repairing floor joists that cannot be inspected until the old floorboards are lifted. If the actual repair takes longer, you pay the difference.

Variations are changes you make to the design or the specification after the price is agreed. Adding extra plug sockets or choosing a more expensive tile will trigger a variation. You must agree the cost of every variation in writing before the builder starts the extra work.

VAT and professional fees

Most work by builders and similar trades is charged at the standard rate of 20 per cent. This applies to most work by builders and similar trades. You can read the official rules on VAT for builders to understand exactly what qualifies.

You may be able to charge the reduced rate of 5 per cent for some work if it meets strict criteria. This includes renovating an empty house or flat, but only if the premises have not been lived in for two years or more immediately before the works start. The full details are explained in VAT Notice 708, and HMRC can confirm whether your project qualifies.

Even if your building work qualifies for the 5 per cent reduced rate, professional services such as architects and surveyors remain standard-rated at 20 per cent. Goods that are not classed as building materials, such as carpets or fitted bedroom furniture, also attract the standard rate. Any work needing planning consent or building control approval that has not been granted is standard-rated by default.

Permissions and building regulations on a renovation

Planning permission and building regulations are two entirely separate systems. Planning permission deals with the appearance of the building and its impact on the neighbourhood, while building regulations ensure the structure is safe and energy efficient. Many projects need one, both or neither.

The Building Regulations 2010 cover the construction and extension of buildings. Building regulations approval is needed for extensions, loft conversions and most structural and services work. Without approval, you will not have the completion certificates you may need when you want to sell your home. Councils can now take enforcement action for up to ten years against non-compliant work. You can check the rules for building regulations approval directly on GOV.UK, and read more about building regulations for home improvements to understand the process.

Approval comes from your local council building control department or a registered building control approver. Certain trades can self-certify their work through a competent person scheme. Gas work needs a Gas Safe registered engineer, and electrical work requires a registered electrician. Always confirm their membership on the scheme's own register. Scotland and Northern Ireland have their own distinct building standards systems, so check your local rules if you live there.

Asbestos and older homes

Houses built or refurbished before 2000 may contain asbestos. This material is highly dangerous when disturbed and must be dealt with by competent people. You should never attempt to remove or dispose of suspected asbestos yourself.

Under the CDM Regulations 2015, domestic building work must be carried out safely. Your health and safety duties as a domestic client normally pass automatically to the builder or main contractor once they take control of the site.

How to budget and keep a contingency

Renovations rarely go exactly to plan. Published advice recommends holding a contingency of 10 to 20 per cent of the total budget, leaning towards 20 per cent for larger or older properties. Agree a figure that suits your own project.

You manage your budget by agreeing stage payments tied to physical progress on site. A schedule might include payments for completing the demolition, pouring the concrete, finishing the first fix and making the building weathertight. You always hold back a final payment until completion.

Completion involves a process called snagging. This is where you inspect the finished house and list minor faults, such as a scratched door frame or a missing spot of paint. The builder must fix these snags and hand over all the necessary certificates before you release the final payment.

Common mistakes and scams to avoid

The building trade attracts rogue operators who prey on inexperienced homeowners. Knowing what to look out for is the best way to protect your money and your property.

Avoid these common mistakes and scams when hiring for a renovation:

  • Choosing a builder on price alone rather than checking their past work
  • Starting work without detailed drawings, a specification or a written contract
  • Handing over large cash deposits before any materials have arrived on site
  • Accepting a rough estimate as if it were a fixed quote
  • Changing the design mid-build without agreeing the extra cost in writing
  • Being told by a tradesperson that building regulations are not needed
  • Accepting cash deals offered without VAT or proper paperwork
  • Failing to tell your home insurer that major building work is happening
  • Paying the final instalment before snagging is finished and certificates are done
  • Hiring cowboy builders who take on more jobs than they can actually staff

The Consumer Rights Act 2015 gives you strong legal protection. It requires tradespeople to carry out their work with reasonable care and skill, for a reasonable price, and within a reasonable time where no timeframe was agreed. If you agree a contract at home, by phone or online, you have a 14-day cooling-off period. Paying by credit card can give you Section 75 protection, which has limits on the price of the item. Citizens Advice is the best signpost for resolving disputes.

Look for builders who belong to recognised schemes. The Federation of Master Builders vets and independently inspects its members, and TrustMark is the government-endorsed quality scheme. You should treat membership of these bodies as a good sign of professionalism, though it is not a guarantee.

Common questions

Do I need a structural engineer for a house renovation?

Structural changes, such as removing a load-bearing wall or altering the roof structure, normally need a structural engineer's calculations. Confirm what your project needs with building control. You can read more about when you need a structural engineer and what they charge to plan your budget.

Do I need planning permission to renovate a house?

Whether a renovation needs planning permission depends on the work and the property, so confirm with your council. Many extensions and loft conversions on houses fall under permitted development rights, provided they stay within strict limits on size, height and position. Flats and maisonettes do not have these rights, and conservation areas or properties with planning conditions are much more restricted. Larger single-storey rear extensions can often go through a prior approval process instead.

How much does a planning application cost?

In England, the standard householder application fee is £548 from 1 April 2026. Most straightforward applications are decided within 8 weeks by the local planning authority. Once permission is granted, work must start within three years in England, or five years in Wales. If you are relying on permitted development rights, a lawful development certificate gives written proof that your project is permitted development.

What is the Party Wall Act?

The Party Wall etc. Act 1996 applies in England and Wales to work on or near a shared wall or boundary. If you are cutting into a shared wall to support a steel beam, or digging foundations close to your neighbour's property, you may need to serve them with notice. Ask your builder or a party wall surveyor whether the Act applies to your plans.

Can I live in the house during a full renovation?

Living through a light refresh may be possible, but a full renovation creates dust and noise and can mean periods without some services. Discuss with your builder whether you can stay, as moving out can make the work easier to plan.

Next steps

Preparing thoroughly before you contact any tradespeople will help you avoid costly surprises and delays once the work begins. Follow a strict process to get your project ready for pricing.

Take these steps to start your renovation safely:

  • Commission professional drawings and a schedule of works so builders can quote accurately
  • Confirm with your local council whether you need planning permission or building regulations approval
  • Arrange a professional asbestos survey if your house was built or altered before 2000
  • Request three written quotes from different builders against the exact same specification
  • Ask to visit the builders' finished jobs and speak privately to their past customers
  • Ask for proof of their public liability and employers' liability insurance
  • Agree a written contract that includes a clear timeline, stage payments and a snagging process

Once your drawings are finished and your budget is set, you are ready to find a builder near you and begin the quoting process.

Find a top rated builder near you

3,554 builders across the UK, each ranked on their Google rating and the number of reviews behind it. Start with your county:

All counties and towns · The UK Top 100 builders

Daniel Hughes
Written by
Daniel Hughes Editor

Daniel is a writer and editor for Top Rated Builders, covering extensions, renovations and building work. When he's not writing guides, he spends weekends walking in the Peak District.

Looking for a trusted builder? Browse our verified listings.

Find a Builder