How Long Does Planning Permission Take and How Long Does It Last?

How long a planning decision takes in England, what happens if the council runs late, how long permission lasts and what you must do to keep it alive before a builder starts.

A calendar, stopwatch, rolled drawing and hard hat on a table.

Most planning applications in England are decided within eight weeks, while larger or more complex ones take up to 13 weeks. Once granted, planning permission generally lasts for three years from the date it is granted, unless the permission says otherwise. This means you generally have three years to begin the development before the permission expires. Check your decision notice for the exact date.

The usual decision time for planning applications

When you submit a planning application, the clock does not start ticking on the day you send it. The eight week period begins only when the council validates your application. Validation means they have checked that you have paid the correct fee and provided all the necessary documents and plans. If something is missing, the council will pause the process and ask you to supply the missing details.

The Planning Portal states that most planning applications are decided within eight weeks of validation. Planning permission and building regulations are two separate systems, and many projects need one, both or neither. Planning permission deals with how a building looks and how it impacts the local area. Building regulations approval is concerned with the structural safety and energy efficiency of the work.

You do not always have to wait for a planning decision. Many extensions and loft conversions on houses fall under permitted development, which allows building within set limits on size, height and position. Flats and maisonettes do not have these rights, and conservation areas, listed buildings and properties with planning conditions are more restricted. If you want written proof that your project is permitted development, you can apply for a lawful development certificate.

For those planning a larger single-storey rear extension, you can sometimes go through a process called prior approval. This is slightly different to a full application but still requires the council to make a decision within a set timeframe. In England, the householder application fee for full planning permission is £548 from 1 April 2026.

When the council takes longer than eight weeks

For applications that are unusually large or complex, the time limit is extended to 13 weeks. The clock follows a valid application, so any delays in providing extra information will hold up your final decision.

If the local authority cannot decide within eight weeks, it should obtain your written consent to extend the period. The council will ask you to agree to a new deadline in writing. If you do agree, this new date becomes the official deadline for your decision to be issued.

This official guidance relates to England, and the planning policy in Wales may differ. Readers in Wales, Scotland and Northern Ireland have their own systems and should check locally to confirm how long decisions take.

What to do if the council is late

If the local authority does not issue a decision within eight weeks, you can appeal for non-determination. This applies unless you have agreed in writing to an extension of that period. Appeals are a last resort and they take several months to resolve, which will significantly delay getting a builder on site.

The time it takes to process an appeal is lengthy. The median time for written representation householder appeals decided in September 2026 was 11.9 weeks, with a mean of 13.7 weeks from 278 decisions. This illustrates how long an appeal adds to your timeline, and you can see the figures in the Planning Inspectorate statistical release. These are monthly figures, real appeals vary, and the timeframe applies to appeals only, not to the original decision.

If your application is actually refused by the council, you can appeal a householder refusal for up to 12 weeks from the date on the decision letter. Again, taking the appeal route means your project will be on hold for months. If you are planning a house renovation, you must factor these potential delays into your schedule.

How long planning permission lasts

By law, any planning permission granted expires after a certain period. Generally, unless your permission says otherwise, you have three years from the date it is granted to begin the development. You should check the decision notice carefully, as the exact expiry date will be printed on it.

If your project was granted outline planning permission, you will have to submit further details for approval before you can build. These are known as reserved matters. Reserved matters approval must be done within three years of the grant of outline permission.

Use that time to finalise your technical drawings, secure your building regulations approval and find a reliable general builder.

Conditions that must be dealt with first

Planning approvals can come with conditions attached by the council. Conditions requiring approval of details not covered in the application must be dealt with before the development can begin. You must not book a builder for a firm start date before all these pre-commencement conditions are cleared.

Getting these details approved takes extra time, so allow for it before a builder is due to start.

If you ignore these conditions and start building anyway, the council could take enforcement action. Ask your council what applies to your permission.

What counts as starting work

Your permission generally lasts three years from the date it is granted, so work must begin within that period. What counts as starting the development, and which conditions must be cleared first, depends on your permission, so ask your council to confirm before you rely on a start date.

Do not assume that a small amount of early work will keep a permission alive. If you are close to the deadline, ask your council in writing what it accepts as a start, and check the decision notice for the exact date. Reserved matters approval after outline permission must be done within three years of the grant of outline permission.

What happens if your permission lapses

If the three year period passes and you have not started work, your planning permission will expire. If you have not started work by then, you will probably need to reapply.

When you submit a new application, the council will judge it against their current planning policies. If the local rules have changed in the three years since your original approval, the council might refuse the new application. A new application will normally carry a fee, which the council will confirm.

To avoid your permission lapsing, you need a realistic timeline. If you want to know more about planning permission for an extension or loft, always confirm the rules with your local council before you make any assumptions.

Planning your builder around the timeline

Getting a builder on site involves a lot of preparation. You should not book a builder for a start date before your planning conditions are cleared and your building regulations approval is in place. Building regulations approval is needed for extensions, loft conversions and most structural and services work. It comes from council building control or a registered building control approver.

A general builder or main contractor will manage the site and bring in the subcontractors they need, such as roofers, plasterers and plumbers. To get an accurate price, builders price from drawings and a specification, not from a cost per square metre. Per square metre figures are only a way to set an early budget, and figures differ widely because some cover a basic shell and others a finished room.

A proper quote requires a specification and a schedule of works. The specification details exactly what materials will be used, while the schedule of works lists the order of the tasks. You should get three written quotes against the same drawings to compare prices accurately.

The table below sets out the planning periods described above.

Project stage

Typical timeframe

Standard application decision

Most decided within eight weeks

Complex application decision

Up to 13 weeks

Discharging planning conditions

Before development begins

Planning permission duration

Generally three years from the date granted

Booking your builder

After conditions are cleared

This table uses the Planning Portal's stated planning periods, and real decision times vary.

Once the builder is on site, the construction phase brings its own timeline. The work is split into first fix and second fix. First fix covers the structural work, making the building weathertight and installing the hidden pipes and cables. Second fix is the visible finishing work, like fitting sockets, radiators and internal doors.

The build ends with snagging. This is where you and the builder walk around the finished project and agree a list of minor faults to fix before you hand over the final payment. The table below shows how long the actual construction phase takes for two common extensions.

Type of extension

Typical build time

Single-storey extension

About 12 weeks

Wraparound extension

12 to 16 weeks

This table shows typical 2026 figures, but real build times depend on design, ground conditions, access and finish.

You must make clear what is normally outside a build quote. You will usually pay separately for kitchens and bathrooms, flooring and decoration, professional fees, planning and building control fees, party wall costs and VAT at 20 per cent. London and the South East cost more, and labour is a large share of any job.

Sometimes a quote will include provisional sums. These are allowances for things that cannot be priced yet, like a specific type of floor tile that you have not chosen. You should also hold a contingency fund of your own to cover variations, which are changes to the design or materials made after the price is agreed.

Common mistakes and scams to avoid

Many homeowners make errors that slow their project down or cause their budget to slip. Avoid these common mistakes when moving from planning approval to the build phase.

  • Starting work without structural engineer's calculations, a specification or a written contract in place.
  • Changing the design mid-build without agreeing the cost in writing, which leads to expensive variations.
  • Being told by a builder that building regulations are not needed, when most structural and services work requires them.
  • Handing over large cash deposits before any materials have arrived on site.
  • Accepting cash deals offered without VAT or paperwork, which leaves you with no paper trail if things go wrong.
  • Choosing a builder on price alone, which often leads to cowboy builders who take on more jobs than they can staff and drag the job out.
  • Accepting an estimate as if it were a quote. A quote is a fixed price, while an estimate is not.
  • Paying the final instalment before snagging is complete and the completion certificates are done.

You must also remember to tell your home insurer about the work before it starts. Under the CDM Regulations 2015, a domestic client's health and safety duties normally pass to the builder. However, if your house was built or refurbished before 2000, it may contain asbestos, which must be dealt with by competent people. Never attempt to remove asbestos, do structural work, or carry out gas and electrical work yourself.

Gas work needs a Gas Safe registered engineer and electrical work needs a registered electrician. Certain trades can self-certify their work through a competent person scheme. You should confirm membership on the scheme's own register and treat it as a good sign, not a guarantee. Trade bodies like the Federation of Master Builders vet and independently inspect their members, while TrustMark is the government-endorsed quality scheme.

If you run into trouble, your consumer rights are protected by the Consumer Rights Act 2015. This law states that tradespeople must carry out work with reasonable care and skill, for a reasonable price and within a reasonable time where none was agreed. You also have a 14-day cooling-off period for contracts agreed at home, by phone or online, and Section 75 protection on credit card payments. Citizens Advice is the official signpost for disputes.

Common questions

What happens with the Party Wall Act?

The Party Wall etc. Act 1996 applies in England and Wales to work on or near a shared wall or boundary. Ask your council or a party wall surveyor whether it applies to your plans, and deal with it separately from planning permission.

Do I need a completion certificate?

If the work needed building regulations approval, you should receive a completion certificate once it is finished. It is the evidence that the work has approval, and you may be asked for it when you sell or remortgage. Ask your council what applies to your project.

How long a house extension takes to build?

If you want to know how long a house extension takes, a typical single-storey extension takes about 12 weeks to build. A larger wraparound extension takes 12 to 16 weeks. These are typical 2026 figures, and your real schedule will depend on ground conditions, access and weather.

Can I start work while waiting for an appeal?

You should not start any work while waiting for an appeal decision. If you build without permission and the appeal is rejected, you risk enforcement action by the council. Always wait for formal written approval and clear all conditions before beginning development.

Your next steps

To move your project forward safely and avoid common delays, follow this checklist before you hire anyone.

  • Wait for your planning decision notice and read every condition attached to it carefully.
  • Deal with any conditions that need approval of details before work begins, and before the three year deadline passes.
  • Get your structural engineer's calculations and full building regulations drawings completed.
  • Ask three different builders to provide written quotes based on exactly the same drawings and specification.
  • Check that the builders are members of a recognised scheme and confirm this on the scheme's official register.
  • Ask to see their proof of insurance and visit their finished jobs to check the quality of their work.
  • Agree a written contract with stage payments, holding back the final instalment until snagging is done.
  • Tell your home insurer about the planned work before any builders arrive on site.

Following these steps ensures you have the right permissions in place and a solid contract to protect your budget. When you have your approved plans ready and you want to start gathering quotes, you can find a builder near you to discuss your project.

Find a top rated builder near you

3,554 builders across the UK, each ranked on their Google rating and the number of reviews behind it. Start with your county:

All counties and towns · The UK Top 100 builders

Daniel Hughes
Written by
Daniel Hughes Editor

Daniel is a writer and editor for Top Rated Builders, covering extensions, renovations and building work. When he's not writing guides, he spends weekends walking in the Peak District.

Looking for a trusted builder? Browse our verified listings.

Find a Builder